Numbers King Doesn't Put in His Newsletter - now just try and get a better deal for Bathgate Park
Rawlson King sits on the Ottawa Public Library Board. It's one of the more consequential seats a Ward 13 councillor can hold right now, because the library system is in the middle of the most expensive, most delayed capital project in its history: the new central library at LeBreton Flats, known as Ādisōke.
You wouldn't know that from his newsletter. What follows is the record — where the project's cost and schedule started, where they stand today, and what taxpayers are paying in the meantime to keep the old Main branch open.
Ādisōke (That'll soak ya): then and now
| Original estimate | Where things stand now | |
|---|---|---|
| Total project cost | Fixed at $175 million — $71 million from the federal government, $104 million from the city — plus $18 million more for a 200-spot underground garage. | Approaching $352 million: nearly double the original budget. Council was asked for another $18.5 million on top of that in May 2026. |
| First major blowout | — | Construction bids in 2021 came in $131 million over the fixed price, pushing the total to $306 million and leaving the city on the hook for an extra $65 million. |
| Opening date | Hoped for as early as 2024, back when the project was first announced. | No public date. As of the most recent staff report, the contractor's own schedule "has not stabilized." A year ago the contractor was targeting completion by this past September — staff still couldn't say when the doors would actually open to the public. |
| City's posture | — | Not ruling out legal action against the contractor. |
Meanwhile: the old Main branch lease
Because Ādisōke isn't ready, the library board has had to keep paying for the building it was supposed to be leaving — the Main branch on Metcalfe Street.
| Extension | Cost to taxpayers |
|---|---|
| Six-month extension, to June 30, 2027 | $900,000 plus taxes |
| Full extension through the end of 2027 (12 months) | $1,800,000 plus taxes |
Why this belongs in the newsletter
None of this is secret. It's in public board reports and it's been covered by CBC and CTV. But a Ward 13 resident reading Councillor King's newsletter wouldn't see any of it — not the budget doubling, not the schedule that "has not stabilized," not the $1.8 million taxpayers are now on the hook for just to keep the lights on at the old building. A library board member is well placed to explain this to constituents. Silence is a choice too.
References
- Josh Pringle, "Ottawa Public Library extends lease at main branch until end of 2027 as Ādisōke faces delays," CTV News Ottawa, Sept. 8, 2026. ctvnews.ca
- "With no set opening for new central branch, Ottawa Public Library extends downtown lease," CBC News, Feb. 2026. cbc.ca
- "Ādisōke library project goes further over budget, faces more delays," CBC News, May 2026. cbc.ca
- "City of Ottawa not ruling out legal action for delayed Ādisōke Library," CTV News Ottawa, June 2026. ctvnews.ca
- "Ottawa's new main library $131M over budget with city on hook for half," CBC News, Oct. 2021. cbc.ca