From Facebook: Jenna Jessup
Why are the track upgrades only coming up now? When did the contractor identify the need for this work, and when did OC Transpo find out? I can’t see that this would be related to the software that just went in so this sounds like a whole separate issue now being identified. If they knew earlier, why wasn’t it built into the testing schedule?
Pre-trial running was already pushed from October to November and still has no confirmed start date. With 21 days of trial running still to follow, it’s looking increasingly unlikely that we’ll be riding the LRT to Orléans in 2026
It looks like a comment or post about delays on the Ottawa LRT (Stage 2) extension to Orléans.
What’s happening with the tracks
According to a memo from OC Transpo General Manager Rick Leary (issued around Nov 18, 2026):
- Full-line testing (trains running the entire length from Tunney’s Pasture to Trim) was set to start on Sunday, Nov 22.
- Contractor East-West Connectors asked for a pause during the week of Nov 29 so they can “advance upgrades to track infrastructure, which will help increase system reliability.”
- Testing on the full line resumes after that week.CTV News
The memo does not describe a specific failure, derailment risk, soft track, geometry problem, or anything comparable to the well-known Stage 1 issues (axle bearings, wheel/rail interface, etc.). It frames the work as a reliability enhancement identified through the staged testing process.
Other issues identified during testing
The same updates note:
- Communications equipment upgrades between trains and the Transit Operations Control Centre (completed the previous week).
- Further work still required to improve reliability of the traction power substation (power system).Ottawacitizen
Timeline and committee context
- At the Transit Committee on Sept 10, 2026, staff said pre-trial running was expected in early October and described the east extension as “progressing as planned.”
- That slipped to November because of safety-critical train control software issues (Hitachi reprogramming), which were addressed with an update on Nov 15.
- Pre-trial running still has no confirmed start date. Leary said he would update Council in December on when it can begin. It is expected to last at least a week, followed by the formal 21-day trial running period, then final safety approvals.
The dedicated Light Rail Subcommittee was dissolved in early 2025; oversight now sits with the Transit Committee. Recent information has come mainly through Leary’s memos to Council rather than a dedicated subcommittee meeting focused on these track upgrades.Cbc
In short, the track work appears to be contractor-requested reliability upgrades surfacing late in the testing phase rather than a major new problem. Combined with the earlier software delay and the remaining pre-trial + 21-day trial running steps, it does make a 2026 passenger opening to Orléans look unlikely.
Officials (in Rick Leary’s Nov 18 memo and the resulting news coverage) have not explained what the actual track work is. They only say the contractor, East-West Connectors, asked for a one-week pause so it can “advance upgrades to track infrastructure, which will help increase system reliability.”
What that usually means in practice
On a light-rail system, “reliability improvements” to track infrastructure typically cover things like:
- Fine-tuning or replacing switch components (the moving parts that let trains change tracks)
- Adjusting rail alignment, profile, or restraining rails
- Ballast work (the crushed stone that holds the ties in place)
- Minor fixes that showed up once they started running multiple trains at closer headways
- Lubrication or friction-management upgrades
These are the kinds of issues that often only become obvious once you put real train traffic on new track for extended periods. They are not usually catastrophic failures — they’re the things that can cause delays, rough rides, higher maintenance, or occasional service interruptions if left alone.
Context from earlier testing
At the September Transit Committee meeting, staff noted they had already seen some challenges with track infrastructure and switches as they increased the number of trains running. The current upgrades appear to be a continuation of that process of “exercising the system” and cleaning up what shows up.
In short: it’s not described as a broken track or a design failure on the scale of the original Stage 1 wheel/rail problems. It’s the contractor saying “we want to make some improvements so the system is more reliable before you start the formal pre-trial and trial running phases.” The vagueness is deliberate — they haven’t publicly said exactly what’s being changed.










