Campaign Video

Https://youtu.be/zBxbnuPAazE

Thursday, 30 July 2026

Oh No! , LRT Woe!

The Bypass Nobody's Proposed — St-Laurent Station
WARD 13 — RIDEAU-ROCKCLIFFE ST-LAURENT STATION FILE

The Bypass Nobody's Proposed

Every mayoral candidate is asking the city to be honest about the St-Laurent shutdown. None of them — and not our own councillor — is asking whether there's a way around it.

Ottawa's own tendering documents now assume it: to fix the ceiling over the tracks at St-Laurent station, the Confederation Line will need to close there completely, in both directions, for five to six weeks — on top of nine to ten weeks of single-track closures before that. The city says construction is probably still two years off. But the plan is already on paper, and the corridor it runs through is one this city spent over a decade telling people to move to specifically because the train was there.

01 / THE FAILUREWhat's actually wrong

St-Laurent's tunnel was built in the 1980s for buses and repurposed for LRT in 2019 without ever being brought up to a comparable standard. Concrete began chipping badly enough to be logged as "severe" as early as 2020. Some of those flagged repairs weren't made until chunks of concrete actually landed on the tracks in January 2024. In May 2024, inspectors found ceiling panels held up by metal framing described as "detached" and "heavily corroded," directly over the platform where riders stand — a discovery that hadn't been caught because the ceiling had gone unchecked since a single inspection in February 2023. A 2025 review added expired expansion joints, one replaced in 2023 at 37 years old, well past its rated life.

A Stantec report commissioned by the city, dated April 2026, says the tunnel now poses a serious and ongoing risk to riders, staff, and the trains themselves. That report sat unreleased for months until a mayoral candidate found it in a subscription tendering portal and brought it to CBC.

Stantec-proposed lower-level closure schedule
Total project duration11–13 months
Single-track closures9–10 weeks
Each direction platform closure4–5 weeks
Full dual-track closure (both directions down)5–6 weeks
Design completion (target)Dec 2027
Construction completion (target)Dec 2029

This city has a well-documented pattern of major infrastructure projects running over budget and behind schedule. The original Confederation Line opened more than 15 months late. Stage 2 has already climbed past $5 billion with repeated contingency top-ups and multi-year delays on the Trillium Line and the east and west extensions. Other high-profile files — the new central library among them — have roughly doubled in cost while slipping a year or more. What reason do residents have to treat the 11–13 month St-Laurent timeline and the December 2029 target as firm rather than optimistic starting points?

02 / THE PROMISEBuilt on the premise of the train

St-Laurent has been a designated Transit-Oriented Development zone since city council approved the plan in 2012. The city has spent the years since actively upzoning around it: a nearly 1,770-unit, six-tower approval southwest of the station in 2025, a 30-storey mixed-use tower proposed along the boulevard in early 2026, both justified in planning documents on the grounds of proximity to rapid transit. People bought and rented in that corridor, some of them recently, on the understanding that the train made a car optional. That was the pitch. The station is the infrastructure the pitch depended on.

03 / THE SILENCEEveryone's talking except the one person representing this ward

Three mayoral candidates went on record within hours of the CBC story. Jeff Leiper, who surfaced the report, called out the city for sitting on it since April without warning residents. Neil Saravanamuttoo called it a breach of public trust and said it shows a city hall that treats residents as an afterthought. Alex Lawson said it fits a pattern of the city letting infrastructure "fall into disrepair" while withholding word of it. All three said they'd release reports like this the moment they land, not months later.

I've seen no statement from Councillor Rawlson King on this — not to CBC, not through his own channels. This is his ward. His constituents are the ones who'll lose the station for six weeks straight. As of publication

04 / THE ASKWhat nobody else has put on the table

The candidates who've spoken up are asking for transparency — tell residents sooner, don't bury the report. That's necessary, but it isn't sufficient. Transparency about a six-week shutdown is not the same as a plan to reduce what that shutdown costs the people who live through it. Nobody has asked the actual engineering question: is there a way to physically route around the failed section of tunnel while it's being fixed, instead of just replacing the train with buses and hoping the schedule holds?

417 / QUEENSWAY CROSSING CYRVILLE ST-LAURENT (TUNNEL) TREMBLAY PROPOSED: STUDY A TEMPORARY BYPASS AROUND THE CLOSED SECTION
FIG. 1 — CONFEDERATION LINE, CYRVILLE TO TREMBLAY. ST-LAURENT SITS DIRECTLY ATOP THE 417 CROSSING — THE SAME PINCH POINT NOW FAILING STRUCTURALLY.

To be clear about the scale of that ask: St-Laurent and Tremblay stations sit about 1.4 kilometres apart, and the reason there's no existing route between them is that the LRT crosses Highway 417 underground right at St-Laurent — the very crossing that's now structurally compromised. A temporary bypass, whether an elevated guideway alongside the highway or a dedicated busway/pedestrian structure, is a real civil engineering undertaking constrained by the 417 right-of-way, utilities, and approvals. It is not a weekend project. I'm not pretending otherwise.

  • Near-term: a real bus-bridging plan, not a vague one. The city's default during past St-Laurent closures has been R1 shuttle buses between Hurdman and Blair. Riders have already said for years that OC Transpo communicates disruptions badly. Before the 5–6 week full closure hits, the city should commit publicly to specific shuttle frequency, capacity, and reliability targets — published in advance, not announced after the fact — so residents can plan around something more concrete than “replacement service will be provided.”
  • Longer-term: cost out a temporary bypass structure and put the number in public. Nobody at the city has studied, or at least published, whether a temporary route around the compromised crossing is feasible or what it would cost against 11–13 months of degraded east-end transit. Given that this corridor was deliberately built up around the promise of this train, the city owes it to those residents to at least know the number before defaulting to buses again.

Study the bypass option, publish the number, and give riders a real bridging plan before defaulting to another multi-week R1 replacement.

Where this stands This isn't a costed commitment — it's a demand that the option be studied and the results published, the same transparency standard other candidates are already asking for on the Stantec report itself. If the number comes back too high, residents deserve to see that too. What they don't deserve is a city that never even asked the question, a councillor who hasn't asked it either, and another project whose optimistic timeline quietly expands the way so many others have.
WARD 13 CAMPAIGN FILE — ST-LAURENT STATION — DRAFT FOR REVIEW
i

Note:

If your councillor's response is merely "something needs to be done". Maybe you need to vote differently?

This time around, inform yourselves, vote differently, vote wisely. Vote for Peter Karwacki for Rideau Rockcliffe.

1 comment:

  1. Placed in the context of Federal Civil service return-to-office this news is grim.

    ReplyDelete