#592 The Proposed Ottawa Hospital - $10 Billion? Not in this lifetime!

At one time MontMartre was considered expensive.... We got'em beat with the hospitals. Total Cost of the project? "No man Knows!"

The Civic Campus Bill: From $2.8 Billion to “Nearly Five Times” That

The Civic Campus Bill: From $2.8 Billion to “Nearly Five Times” That

Ontario’s infrastructure minister says the province alone is now investing close to $10 billion in The Ottawa Hospital’s new Civic Campus. Nobody has yet said who covers the rest.

This week, Ontario Infrastructure Minister David Piccini told a legislative committee that the province’s investment in the new Civic Campus is approaching five times the original estimate, or nearly $10 billion. The original project cost was $2.8 billion, of which the province was to provide $2.1 billion.

When Blais, a questioner at the committee, asked him to account for “a five-X increase in costs,” the minister’s explanation was a brief reference to supply chains. The Ministry of Health later said only that the project is complex and that it is working with the hospital and Infrastructure Ontario to ensure it is “competitively priced.”
To be clear...No updated total project cost has been published.

Before and after

ItemOriginal projectionLatest public information
Total project cost$2.8 billionNo official updated total. Minister’s figure for the provincial share alone is nearly $10 billion.
Provincial share$2.1 billionNearly $10 billion (minister’s statement to committee)
Local (community) shareAbout $687–700 millionNot confirmed. Blais estimated at committee roughly $2.25–2.5 billion. That is his estimate, not an official figure.
Ask of City of Ottawa$150 million (2022 request)Undecided. Left to the council elected Oct. 26. The mayor says the city will not cover “billions and billions” in added cost.
Foundation fundraising$500 million goal$404 million raised so far
Construction start2024Site preparation under way. Main hospital building not yet built.
Opening2028Critics and a project consultant point to well into the 2030s. An updated timeline is expected in the coming months.

The “nearly $10 billion” figure applies to the provincial investment only. It should not be read as the total project cost, which has not been published. Percentages: $10B is about 4.7 times the province’s original $2.1B share and about 3.6 times the original $2.8B total.

Who will pay for it?

The original funding model was simple. Ontario would cover $2.1 billion. The community would raise roughly $700 million through the Ottawa Hospital Foundation’s campaign, plus revenue such as parking and retail fees. The City of Ottawa was asked for $150 million, the largest funding request it had ever received.

That model no longer matches the numbers being discussed. Several things are unresolved:

  • Does the province absorb the whole increase? The minister’s figure suggests the provincial share has grown enormously, but the ministry has not said whether the local share is fixed at its original amount or grows too.
  • What happens to the local share? If it grows in proportion, the foundation cannot close the gap through donations alone, which leaves the question of whether municipal property taxpayers are asked to contribute more.
  • What will the new council decide? The $150 million request sits with the council elected on Oct. 26. The mayor has drawn a line against open-ended additional costs, but there is no published proposal on what the city would or would not fund.

In the end, every dollar comes from taxpayers.
Whether it comes through the provincial treasury, which Ottawa residents also fund, or through the city’s property tax base is the open question, and it is one the public is entitled to see answered with a real budget.

What to watch for

  • A published, itemized total project cost and the reason for each change from $2.8 billion.
  • The updated construction and opening schedule, expected in the coming months.
  • A staff report to the new council on the city’s contribution.
  • A clear statement from the province on how it splits any increase with the local share.

One piece of the project is physically done. The parking garage, built first so crews had somewhere to park, was expected to open this summer. The hospital itself is the part still without a final price.

Sources

Ottawa’s Forecasting Problem: The Numbers Keep Missing

Ottawa’s Forecasting Problem: The Numbers Keep Missing

Libraries, light rail, a stadium, a transit system and now a hospital. The City of Ottawa’s capital and operating forecasts have missed again and again, and the pattern matters more than any single project.

The question on the new Civic Campus is why a $2.8 billion project turned into a number the minister puts near $10 billion for the province alone. But Ottawa has seen this movie before. Looking across the city’s own major projects and its transit operating budget, the same thing keeps happening. A number is announced to win approval, and a different number arrives later.

Capital: the first number is rarely the last

ProjectOriginal figureLater figureChangeWhat was said about why
Ādisōke central library $192.9M (2018, including parking) $352M (latest request) About +82% Construction-market inflation, higher bids, delays, and later oversight and contingency needs
LRT Stage 2 $3.6B (early estimate); $4.66B at 2019 approval Over $5B in the 2026 draft budget About +39% or more from the early estimate; 7% or more since approval Delays, legal fees, claims and contingency top-ups. Council has topped it up at least twice.
Lansdowne 2.0 $332.6M (2022 concept-level estimate) $419M (Nov. 2023); auditor general said $493.4M (2024); approved at $418.8M (2025) About +26% from concept to approved figure Auditor general: cost estimate “optimistic” and contingency too thin
Civic Campus (hospital and province, not the city) $2.8B total; $2.1B provincial Minister says provincial investment is nearly $10B; ministry would not corroborate About 4.7 times the provincial share, if accurate Minister cited supply chains. No updated total has been published.

Percentages are my arithmetic from the figures in the linked reports. Lansdowne 2.0 is the closest to a counter-example: the city’s director of infrastructure services told councillors in 2026 that it is on schedule and within budget. The auditor general’s higher figure has not so far been borne out.

Officials gave explanations that are partly fair. On the library, the city said the increase came from factors staff could not have predicted, and the report blamed construction inflation running well above what was assumed. On Lansdowne, Mayor Sutcliffe made the point that the $419 million figure was an estimate, and so was the auditor’s. These are reasonable observations about uncertainty. But they raise the real question. If estimates are uncertain, why are they presented to council as single numbers?

Operating: revenue assumptions that didn’t hold

The operating side shows the same habit, most clearly at OC Transpo, where budgets assumed ridership and fare revenue that did not materialize.

ItemForecast or assumptionWhat happened
OC Transpo 2025 result Staff anticipated a $36M deficit going in Projected at $46.6M mid-year; $52M at year-end, with fare revenue $20.2M below budget, up from $25M in 2024
How the 2025 gap was covered Provincial and federal funding expected It did not arrive; the city drew $44.9M from its tax stabilization reserve and $7M from the transit reserve
Long-term ridership and fares 2019 long-term financial plan assumed a much stronger recovery Staff said in 2023 that 25-year fare revenue would be $3.7B lower and pre-pandemic ridership would not return until 2030
2026 ridership Pre-2030 recovery path Ridership averaged 67% of pre-pandemic levels in January to June; a $12.35M deficit is forecast

The rest of the city came in better. In 2025, tax-supported programs finished with a $31.9M surplus, and without the transit shortfall the city’s overall result would have been a $15M surplus. The problem is concentrated, not general.

Note the sequence. In 2023 staff reset the ridership outlook and said recovery would take until 2030. Two years later fare revenue was still short of budget by $20 million, and in 2026 ridership is still around two-thirds of the pre-pandemic level. A forecast that gets reset and then misses again is a forecast with an optimism problem, not a one-time shock.

Why it matters

  • Decisions are made on the first number. Councils approve projects against an initial estimate. By the time a higher figure arrives, the site is excavated and the alternatives are gone. Staff have said as much: with a project well advanced, there is little choice but to finish.
  • Overruns crowd out other spending. Every added dollar on one project is a dollar the city cannot put toward roads, recreation or transit service, or a reason to raise taxes.
  • Tax targets sit uneasily with weak forecasts. Council sets a headline property tax target before departments finish building their budgets. When revenue assumptions miss, as at OC Transpo, the gap is covered from reserves or later increases.

What better forecasting would look like

These are process changes, not a position on any particular project:

  • Present estimates as ranges, with the estimate class and the contingency stated, and not as a single figure.
  • Compare each project against completed comparable projects, so that the history of overruns informs the starting number.
  • Get an independent cost review before council votes, not after, as happened with Lansdowne.
  • Publish one annual page comparing every major forecast with the actual result.
  • Give revenue forecasts, including transit fares, a stated downside case and the reserves that would be used if it occurs.

The hospital is the next test

The Civic Campus design is, according to the hospital, complete, and its costs are still being finalized. Whatever number emerges, the useful questions are the same as above. What range was the original $2.8 billion based on? What changed, line by line? And who is on the hook for the difference? Ottawa’s record says to ask before the shovels are in the ground, not after.

Sources

#593 I said the numbers would move. They moved.

I said the numbers would move. Boy did they move.

I take no joy from any of this.

In July I wrote that the new Civic Campus belonged on the list of off-balance-sheet pressures facing the next council. The city had been asked for up to $150 million as part of a roughly $700 million local share on an original $2.8 billion total. Staff were still finalizing design, cost, and schedule. The parking garage was advancing; the hospital proper was not. Opening was already expected to slip into the 2030s. Cost-escalation risk was obvious. That $150 million (or higher) was not yet a recorded liability, but it was a known claim on future tax and rate revenue that would compete with everything else.

I was running for Ward 13. The post was one of several that treated the hospital the same way I treated the library, LRT Stage 2, Lansdowne, and the rest: as a number that had been presented, and a number that was likely to change.

During the campaign the main mayoral candidates, when they addressed the hospital at all, stayed inside the old frame. The hospital is needed. Health care is a provincial responsibility. The city will look at a detailed request if one arrives. They did not highlight the escalation risk or the delay risk that was already visible in the public record. They did not fold the ask into the broader stack of claims on the same limited revenue streams. That was a choice.

This week the provincial infrastructure minister told a legislative committee that the province is now investing “just shy of $10 billion” in the project. That is roughly 4.7 times the original $2.1 billion provincial share. The Ministry of Health has not confirmed the figure. The hospital says design is complete and that timelines and costs are still being finalized. No updated total project cost has been published. An MPP estimated that a proportional local share would now sit between roughly $2.25 billion and $2.5 billion. The foundation has raised about $404 million of its $500 million goal. The mayor has said the city will not cover “billions and billions” in added cost.

The $10 billion number was not available before voting. The pattern was.

Item What was public before election day What is public now
Total project cost $2.8 billion (original) No official update published
Provincial share $2.1 billion Minister: just shy of $10 billion
Local share ~$700 million Unconfirmed; one estimate $2.25–2.5 billion if proportional
City ask Up to $150 million (2022) Still pending; mayor drawing a line against open-ended overruns
Opening Originally 2028 Critics and project advisors: well into the 2030s
Construction status Site preparation; main building not started Same, with contracts still being finalized

This is the same sequence Ottawa has seen on other files going as far back as the Rideau Canal and Colonel By. A number is used to secure approval or to keep a project moving. A different number arrives later.
Explanations are offered: supply chains, development charges, complexity, inflation. Some of those explanations are fair. They do not change the arithmetic or the fact that the first number is the one that shapes the political conversation.

I flagged the risk in July because the risk was already in the documents. The documents have not become kinder since then. Every additional dollar still comes from taxpayers—whether through the provincial treasury (which Ottawa residents also fund) or through the city’s property-tax base. The open questions are the same ones that were open before the election: the published total, the split between provincial and local shares, the schedule, and whether the city will be asked for more than the original $150 million.

The next council will receive a staff report on the city’s contribution. An updated total and timeline are expected in the coming months. Those documents will either confirm the pattern or break it. I will read them either way.

I take no joy from the increase. The hospital is still needed. The costs are still real. The forecasting habit is still the same one I wrote about months ago.

i
Shown left, the Wuhan Hospital, precovid, built in two weeks.

4 comments:

  1. Put that in the context of Bathgate Park wanting a lousey basketball court.

    ReplyDelete
  2. Just to be clear, the mayor’s post-election statement that the city will not cover “billions and billions” removes the largest risk. It does not remove the interest cost on whatever amount is ultimately approved.

    That cost is an annual claim on the same tax room his 2.5 % promise is meant to protect. The staff report on the hospital contribution and the 2027 budget documents will show whether that claim can be absorbed without breaching the ceiling or whether the ceiling itself is adjusted.

    My prediction...it will not.

    ReplyDelete
  3. Let me make this even more clear... a 10 billion dollar hospital (and that is the base not the top line) wil NOT make people healthier...and it likely will make them sicker. Why?

    Beccause this obscene expenditure leaches cash away from the sicial services that really make the difference...housing, efucation, proper nutrition, family health, public transit, affordability.

    Anyway it is income- not hospitals or dictors that makes people healthy. And it is education that impacts income.

    ReplyDelete
  4. The health ministry specifies hospital development projects follow a standard construction cost-sharing formula: provincial government 90 per cent
    local 10 per cent

    If the Ottawa Hospital’s new Civic Campus follows the same cost-sharing formula as every other hospital project in the province...that's $1.1 billion!!!!